Kitchen Replacement Contract 2006-07

This contract was set up in 2006. It was the first of a new type of contract whereby we established a longer term agreement with a Contractor to replace ~45 kitchens a year for a number of years. In the past we had a contract every 3 or 4 year where a Contractor would replace maybe 120 kitchen in a few months. There are many advantages to this new way.

bulletFor the Contractor the work is guaranteed for several years.
bulletWe can use different types on Contractor, large or small. Small can do one kitchen per week, Large can do four per week, if they choose.
bulletWe can easily add extra properties to the contract. (Previously, ‘one off’ kitchens were expensive to do.)
bulletIt’s easier to get the Contractor back to do repairs.
bulletThe cost is spread over each year, rather than having very large spends every 3~4 years.

The Quantity Surveyor was appointed in May 2006. Mathieson Partnership were chosen.

The Property Management and Development Sub-Committee viewed kitchen units from several suppliers and choose Moore ’s Kitchens as supplier.

Various open days were held in the Sheddocksley area to allow Members to choose the colours and design of their units. Moore ’s then visited each of our Member’s home to design the kitchen to meet their needs.

Following a tender the contract was awarded to Richard Duthie & Sons, Peterhead.

Work started in September 2006.

49 kitchens in the Sheddocksley area were in the first year’s programme

In 2007 further open days were held for the second phase of the contract

35 kitchens in the Balmedie and Northfield area were in the second year’s programme.

The contract progressed well, and Members had very few complaints. The results of the questionnaires are below.

Kitchen 45 Replacement Contract (Sheddocksley)

Info provided by TF before contract

Very Satisfied

35%

84%

Satisfied

48%

Not Sure

10%

10%

Dissatisfied

3%

6%

Very Dissatisfied

3%

Info provided by contractor before contract started

Very Satisfied

32%

84%

Satisfied

52%

Not Sure

10%

10%

Dissatisfied

3%

6%

Very Dissatisfied

3%

Quality of workmanship

Very Satisfied

76%

97%

Satisfied

21%

Not Sure

0%

0%

Dissatisfied

3%

3%

Very Dissatisfied

0%

& friendliness during contract

Very Satisfied

72%

93%

Satisfied

21%

Not Sure

3%

3%

Dissatisfied

3%

3%

Very Dissatisfied

0%

Info provided by contractor during contract

Very Satisfied

35%

87%

Satisfied

52%

Not Sure

10%

10%

Dissatisfied

3%

3%

Very Dissatisfied

0%

Info & assistance provided by TF during contract

Very Satisfied

30%

77%

Satisfied

47%

Not Sure

17%

17%

Dissatisfied

3%

7%

Very Dissatisfied

3%

Progress of contract once work had started

Very Satisfied

65%

87%

Satisfied

23%

Not Sure

0%

0%

Dissatisfied

10%

13%

Very Dissatisfied

3%

Overall satisfaction with the finished work

Very Satisfied

76%

90%

Satisfied

14%

Not Sure

7%

7%

Dissatisfied

3%

3%

Very Dissatisfied

0%

Total No. of Replies

31

Total No. within Contract

49

Kitchen 45 (Pt2) Replacement Contract (Balmedie) 

Info provided by TF before contract

Very Satisfied

27%

91%

Satisfied

64%

Not Sure

9%

9%

Dissatisfied

0%

0%

Very Dissatisfied

0%

Info provided by contractor before contract started

Very Satisfied

36%

91%

Satisfied

55%

Not Sure

9%

9%

Dissatisfied

0%

0%

Very Dissatisfied

0%

Quality of workmanship

Very Satisfied

64%

100%

Satisfied

36%

Not Sure

0%

0%

Dissatisfied

0%

0%

Very Dissatisfied

0%

& friendliness during contract

Very Satisfied

67%

100%

Satisfied

33%

Not Sure

0%

0%

Dissatisfied

0%

0%

Very Dissatisfied

0%

Info provided by contractor during contract

Very Satisfied

45%

91%

Satisfied

45%

Not Sure

9%

9%

Dissatisfied

0%

3%

Very Dissatisfied

0%

Info & assistance provided by TF during contract

Very Satisfied

36%

73%

Satisfied

36%

Not Sure

18%

18%

Dissatisfied

9%

9%

Very Dissatisfied

0%

Progress of contract once work had started

Very Satisfied

73%

100%

Satisfied

27%

Not Sure

0%

0%

Dissatisfied

0%

0%

Very Dissatisfied

0%

Overall satisfaction with the finished work

Very Satisfied

64%

100%

Satisfied

36%

Not Sure